North Portsea Island Phase 4b Update - Week 12
The works at the Andrew Simpson Centre slipway are almost finished and then the centre can start using the new slipway.
More Details -
North Portsea Island Phase 4b Update - Week 11
Concrete is like goldilocks’ porridge – conditions can’t be too hot or too cold – they need to be just right!
More Details -
North Portsea Island Phase 4b Update - Week 10
We have just completed the first upper wall section, click here to read more
More Details -
North Portsea Island Phase 4b Update - Week 9
At the Andrew Simpson Watersports Centre the scheme is rebuilding a section of the slipway and adding a flood gate at the top of the slipway.
More Details -
North Portsea Island Phase 4b Update - Week 8
At the Andrew Simpson Watersports Centre the scheme is rebuilding a section of the slipway and adding a flood gate at the top of the slipway.
More Details -
North Portsea Island Phase 4b Update - Week 7
At the Andrew Simpson Watersports Centre the scheme is rebuilding a section of the slipway and adding a flood gate at the top of the slipway.
More Details -
North Portsea Island Phase 4b Update - Week 6
This week we have seen the walls being formed using a textured mould to provide shelter for marine life to settle
More Details -
North Portsea Island Phase 4b Update - Week 5
This week has been busy this week! Several concrete pours have taken place as the construction of the flood wall continues along the frontage and more.
More Details -
North Portsea Island Phase 4b Update - Week 4
The slipway at Andrew Simpson Watersports Centre has been progressing well, with the final pours currently underway. We have also had a drone out on site this week to take some pictures
More Details -
North Portsea Island Phase 4b Update - Week 3
This week the team have been continuing to progress well along the frontage at North Portsea Island.
More Details -
North Portsea Island Phase 4b Update - Week 2
This week has seen the first concrete wall pours happening on site near the Andrew Simpson Watersports Centre.
More Details -
North Portsea Island Phase 4b Update - Week 1
Team have made a fantastic start back on site at Phase 4 (Eastern Road) works. Works have begun adjacent to the Andrew Simpson Watersports Centre and to the area to the south of the slipway.
More Details