North Portsea Island Phase 4b Update - Week 17
We are approaching the end of the construction season: we are required to stop works on the foreshore end of September, due to overwintering birds. But we can continue landscape works over winter.
Works continue at the Tudor Sailing Club slipway, which will be finished in good time before we finish our construction season at the end of September.
The coastal defence wall north of the sailing clubs towards Kendalls Wharf and south of the sailing clubs up to Harbourside Park are progressing well. Next month, we will begin work to install the glass flood wall at the Andrew Simpson Centre and Tudor Sailing Club.