North Portsea Island - Eastern Road and Kendall's Wharf, Phase 4

We are building new flood defences for Portsea Island!

Npi4 Logo Header Banner2 Npi4 Logo Header Banner2

If you would like to hear more about the works happening in Portsmouth, sign up to our newsletter.


Phase 4 – Eastern Road

Last year we completed the first section of Phase 4, including all landscaping works. The area completed was by Kendall’s Wharf, towards the northern end of Eastern Road. The site was approximately 300m long, and works included raising ground levels of footpaths and a road, as well as building the first section of a wall which will run down to Milton Common once works are complete. The northernmost section connects with previously completed Phase 1 Anchorage Park scheme. Landscaping works were also completed with new wildflowers and trees along the length of the footpath and road. Check out the pictures to see the construction and completed works!

Now we are working our way south along Eastern Road, we will be constructing through the summers of 2021 – 2023. The construction of these works is restricted to summer months due to ecological constraints during the winter months (October – March). Protected birds spend the winter in Langstone Harbour and the surrounding areas, so we ensure that minimal disturbance occurs to them. These works will give the area a new sea wall, a new, wider footpath as well as areas with a glass flood wall. There will also be areas of seating and enhanced landscaping, alongside many environmental enhancements. You may notice as the wall is being built that the seaward side of the wall is textured, this is called an ‘ecoformliner’. This textured surface allows for retention of water, which encourages habitat growth – learn more on our environmental enhancements page, where you will also read about even more enhancements that we’re including.

Works planned for spring/summer 2021 at Harbourside Park:

  • A new fence that will be installed to separate Harbourside Park from the working area. The fence will not affect the current view.
  • The footpath level will temporarily be reduced and widened to enable the team to prepare the wall.  
  • A horizontal sawcut will be made in the existing wall to prepare it for works next year. This does not increase the flood risk and the wall will still be fully functional. The saw cutting equipment will have a water feed attached to it to help dampen down the dust. 

Works planned for spring/summer 2022 at Harbourside Park:

  • A sheet pile wall will be installed to help form the base for the glass flood wall.
  • Prior to piling works, a condition survey will be undertaken, including an inspection and photographic record of the local area. 
  • The concrete base will then be formed, and the glass flood wall installed.
  • These works are planned from 01 April 2022 to September 2022.