North Portsea Island Phase 4b Update - Week 18
Tudor Slipway Progress update: “blinding” work guys!
The piling work is complete and blinding work is currently underway. Blinding is a layer of concrete between the sub base for the slipway (fill material) and the structural concrete surface slab, which you see when the slipway is complete.
Once sections of blinding are complete we will start works on the concrete base slabs and pouring concrete for the edge walls of the slipway.