Hampshire County Council Repair Works in Langstone
Hampshire Highways undertaking safety repair works to the footpath near Langstone High Street, starting Monday 9th May.
More Details -
Langstone Coastal Defence Scheme Update - Oct 2021 Update
Since completion of the Phase 2 Ground Investigations earlier this month, we have had a couple of reports of a short section earth bund on the western side of Langstone Rd being inadequately reinstated.
More Details -
Langstone Coastal Defence Scheme Update - Oct 2021
Ground Investigation (GI) works are complete and the next stage of structural investigations at Langstone, scheduled for the week commencing Monday 4th October 2021.
More Details -
South Hayling Beach Management - Sept 2021
Notification of forthcoming works along the South Hayling Frontage
More Details -
Langstone Coastal Defence Scheme Update - Sept 2021
Ground Investigation (GI) works are scheduled to take place in Langstone week commencing Monday 13th September 2021
More Details -
South Hayling Timber Maintenance: Coastguard Revetment Works
Notification of forthcoming works along the South Hayling Frontage
More Details -
Langstone Coastal Defence Scheme Update - July 2021
Coastal Partners and consultants AECOM will be hosting Community Participation Evenings for the Langstone FCERM Scheme on July 21st and July 22nd, between 4pm and 7pm.
More Details -
Langstone Coastal Defence Scheme Update - May 2021
Since our last update, the project team have been preparing to appoint the specialist support of professional services to deliver the development of the project through the next phase of detailed design.
More Details -
Update - South Hayling Beach Management
Following completion of our beach management activities throughout February at Eastoke, stormy weather affected the south coast of England. The beach bore the brunt of these storms and prevented flooding from occurring
More Details -
Update - West Beach Emergency Repairs
Groyne 54 at West Beach has now been completely removed.
More Details -
Update - West Beach Emergency Repairs
Remaining section of the ineffectual timber groyne to be removed on Thursday 25th February, during the afternoon tide.
More Details -
Update - West Beach Emergency Repairs
Before low tide this morning our contractor started removing the ineffective groyne at West Beach.
More Details