Alverstoke Coastal Defence Scheme - January 2022 Update
The scheme to the improve flood defences at Alverstoke commenced in January 2022.
More Details -
North Portsea Island Phase 4b Update - Week 27 and 28
Work has been carried out over the past few months and whilst pausing all work close to the sea during the winter break, some landscaping work will still be conducted in the area around the sailing club.
More Details -
Langstone Coastal Defence Scheme Update - Oct 2021 Update
Since completion of the Phase 2 Ground Investigations earlier this month, we have had a couple of reports of a short section earth bund on the western side of Langstone Rd being inadequately reinstated.
More Details -
North Portsea Island Phase 4b Update - Week 25 and 26
The opening of the slipway at the sailing club marks one of the last milestones of work before pausing for winter.
More Details -
Langstone Coastal Defence Scheme Update - Oct 2021
Ground Investigation (GI) works are complete and the next stage of structural investigations at Langstone, scheduled for the week commencing Monday 4th October 2021.
More Details -
North Portsea Island Phase 4b Update - Week 23 and 24
Last week the highly anticipated flood glass arrived on site and the first sections of glass flood wall are being installed at the Andrew Simpson Centre.
More Details -
North Portsea Island Phase 4b Update - Week 22
We pause our main construction works over the winter months as there are a number of bird species that migrate through and also overwinter in the Solent, which are protected.
More Details -
Hook Lake Coastal Management Study - Community Engagement
In Summer 2021 we launched a visitor survey to seek the community’s views on Hook Lake with Warsash Nature Reserve. Here are the top five answers to these key questions.
More Details -
North Portsea Island Phase 4b Update - Week 21
This week the spring tides have reached the new wall, and a nice reflection was visible in the water.
More Details -
South Hayling Beach Management - Sept 2021
Notification of forthcoming works along the South Hayling Frontage
More Details -
Langstone Coastal Defence Scheme Update - Sept 2021
Ground Investigation (GI) works are scheduled to take place in Langstone week commencing Monday 13th September 2021